Day 20: (Mon Apr 1, Week 12) Mid-Project Review

Notes for 2024-04-01.

Administrative

The 3D printing system is running normally, although further repairs are needed for full capacity (four printing units). Prints may be submitted via Project 3D Printer Submissions.

  • Week 12: start second full system iteration

  • Week 13: (no class Mon Apr 8) system integration

  • Week 14: final prototype refinement, public demo

  • Week 15: documentation and critique

Agenda

  1. Each student should present their progress to date to the whole class. (Project Update 4 Shared Folder).