Final Projects – IDeATe: Inflatables https://courses.ideate.cmu.edu/99-361/s2023a CMU | 53-330A Wed, 24 Jan 2024 02:02:39 +0000 en-US hourly 1 https://wordpress.org/?v=6.1.6 https://courses.ideate.cmu.edu/99-361/s2023a/wp-content/uploads/2017/12/cropped-CMU-inflatables-S18-web-image2-5.jpg Final Projects – IDeATe: Inflatables https://courses.ideate.cmu.edu/99-361/s2023a 32 32 Final Project Details/Timeline: June, Elin, Neha, Adrienne https://courses.ideate.cmu.edu/99-361/s2023a/final-project-details-timeline-june-elin-neha-adrienne/ https://courses.ideate.cmu.edu/99-361/s2023a/final-project-details-timeline-june-elin-neha-adrienne/#respond Mon, 03 Apr 2023 16:26:26 +0000 https://courses.ideate.cmu.edu/99-361/s2023a/?p=9086 Continue reading "Final Project Details/Timeline: June, Elin, Neha, Adrienne"]]> Proposed Timeline for Final Project:

4/3 – 4/7 : Finish muslin prototype, finalize patterns and overall vision of inflatable. Gather fabric needed for inflatable.

4/10 – 4/14: Finish laser cutting and dyeing pieces. If there’s time, begin sewing.

4/17 – 4/21: Sew inflatable and experiment with different embellishments (LED lights, flying parts within, etc)

4/24 – 4/28: Test with fan and make last-minute adjustments.

Materials Needed:

890 square feet of ripstock: all white
Colored Dye: red, blue, purple, yellow, green
Two fans, 12 sandbags

]]>